Construction Update 4/26/19 (Click for more)

Holmes School Week of April 15th
 Mechanical contractor set the roof top units for the new addition. Installed tubing for the in-slab radiant heating on the second floor.
 Rough-in electrical conduits overhead on the first floor
 Framing the exterior walls on the west elevation of the building. Installing the exterior sheathing on the south elevation walls.
 Poured the second floor concrete floor slab and installed the spraylock moisture mitigation product.
 Roofers built the knee wall located on the roof.  Mason began the waterproofing of the exterior sheathing at the courtyard walls.
 Plumber installing floor drains and hangers.

construction

Week of April 22nd
 Poured the first floor slab on grade concrete and installed the spraylock moisture mitigation product.
 Continued electric overhead rough-in on first and second floors. Finalized the temporary lighting on the second floor.  Mason is continuing the installation of the waterproofing of the exterior sheathing/walls in the courtyard.
 Continuing to frame the exterior wall along the west elevation. Finishing the sheathing on the south elevation and beginning to sheath the exterior west wall. Began the layout of the second floor interior walls.
 Roofers began installing roof insulation and roof membrane.

construction1

Westview Hills Middle School
Week of April 15th
 Installing the metal stud framing for the exterior walls on the east side of the addition.
 Electrician continuing to complete home-run conduit work on the interior of the existing building during second shift. Installed the temporary lighting in the addition.
 Plumbers installing the toilet carriers and rough-in in the bathrooms of the addition. Tying in the roof drains of the addition.  Roofers installed the roof of the new addition.
 Mechanical contractor began installing the gas lines and ductwork hangers throughout the addition.

Week of April 22nd
 Continuing to install the metal stud framing for the exterior walls, on the west side as well as the clearstory.
 Electrician is continuing the home-run conduit installation work on the interior of the existing building. Continuing the rough-in of conduit in the addition.
 Plumbers are continuing the rough in of vent piping throughout the addition in preparation of the masonry wall work which is beginning next week.
 Mechanical contractor continues to install pipe and duct hangers throughout the addition.