Construction Update 5/9/19 (Click for more)

Holmes School Week of May 6th
 Mechanical contractor continues to install ductwork on the second floor. Has begun installing the ductwork on the first floor. Continuing to install hot water piping on first and second floors.
 Continuing to rough-in electrical conduits overhead on the first floor and on the second floor.
 Plumber has installed the toilet carriers and other in-wall sanitary and water piping for the second-floor gang restroom.
 Drywall contractor is installing top track on the second floor is 80% complete with the layout of the first-floor walls/chases.
 Exterior framing and sheathing has been completed on the vertical walls. Continuing to frame and sheath the soffits.
 Roofer has completed all but the perimeter edge roofing.  Mason has installed the second-floor bathroom walls. Continues to complete detailing for air/vapor barrier installation. Do to both predicted as well as actual rainfall this week, Mason could not continue on the fluid applied air/vapor barrier.

Westview Hills Middle School Week of May 6th
 Drywall contractor completed the sheathing of the exterior vertical surfaces. Continues to frame for the soffits. Completed the sheathing of the knee wall in the courtyard.  Electrician is continuing the home-run conduit installation work on the interior of the existing building. Prepared conduit for rough-in into the masonry walls in the science rooms of the addition. Continued installing other rough-in conduit throughout the addition.
 Plumbers continued to install overhead rough-in and is working with mason relative to vent, sanitary and water piping in the bathrooms of the addition.
 Mechanical contractor continued the installation of the hot water piping, gas piping for the science classrooms. Started installing ductwork in the addition
 Site contractor completed the tie-in of the building to the new storm structure on the north side of the building.