Construction Update 6/7/19 (Click for more)

Holmes School Week of June 3rd

 Mechanical Contractor continues the installation of insulation on the second-floor ductwork and piping in the corridors. Continuing to rough-in piping and ductwork on the first floor. Rough-in of ductwork and piping on the first floor will be completed next week.
 Continuing to rough-in electrical conduits overhead on the first floor and on the second floor. Installing all back boxes and TV boxes on all floors. Began pulling wire on the second-floor lighting.
 Continuing with plumbing installation on the first floor.
 Drywall contractor continues hanging drywall in the second-floor corridor. Starting to hang drywall on the first floor.
 Drywall contractor continues the installation of the nail base insulation that will be behind the metal panels.
 Mason has removed scaffold in the courtyard area. Continuing to install brick on the south and west elevations. Finished the brick washing of the courtyard as well as the north elevation.
 Demolition has begun in the existing B-wing.

Westview Hills Middle School Week of June 3rd

 Electrician is continuing the home-run conduit installation work on the interior of the existing building. Prepared conduit for rough-in into the masonry walls in the science rooms of the addition. Continuing installation of TV boxes through the addition.
 Mechanical contractor continued the installation of the hot water piping, gas piping for the science classrooms. Ductwork in the addition is continuing. Continued the insulation of the ductwork.
 Mechanical contractor started laying out the work of the renovation in Areas A and B.
 Mason continued brick work on east elevation.
 Demolition work has begun in Areas A and B.
 Abatement work has begun