Construction Update 6/24/19 (Click for more)

Holmes School Week of June 17th

 Mechanical rough-in work in the new addition has been completed. Insulation of ductwork and piping is continuing. The rough-in work in area C (existing boiler room) is ongoing.
 Continues to pull wiring throughout the building.
 Plumbing rough-in work has been completed in the addition. CMI worked on installing two new roof drains in area C as well as run new overhead domestic water line in C.
 Drywall contractor continues hanging drywall in the second-floor corridor. Continues to hang drywall on the first floor. Has started taping and mudding walls on the second floor.
 Brick work on the addition has been completed.
 Curtainwall installation continued in the courtyard area of the addition. The curtainwall frames are 100% complete in this area with glass approximately 75% complete.
 Demolition was completed in the existing B-wing.
 Top track of the stud framing in the existing B-wing was installed.

Westview Hills Middle School Week of June 17th

 Electrician is pulling wiring through-out the addition. Completed demolition of electrical items throughout the renovation portion as required.
 Mechanical contractor continued insulation of duct and water lines in the addition. Started the rough-in of ductwork in both area A (band area) and Area B (library area).
 Plumber has completed approximately 50% of the underground plumbing in the renovation areas A and B.
 Mason finished all brickwork on the addition.
 Demolition work was completed in the areas A and B.
 Steel contractor has provided shoring and has begun modifying columns and beams in the future auditorium space.
 Concrete contractor excavated and installed footings in the cafeteria area of the renovation.