Construction Update 7/26/19 (Click for more)
Holmes School Week of July 22nd
Boiler, water heater, pumps, and expansion tanks were all set in the Area C boiler room.
Electrician has continued pulling wire for power and lighting throughout the addition as well as pulling low voltage cabling.
Drywall contractor has completed the taping and mudding of the first floor classrooms and corridors. Taping still remains to be completed in the Multi-Purpose room. Drywall has been installed at the header locations throughout the area B renovation work. Has also completed the installation of drywall in the multi-purpose room.
Curtainwall frames and glazing continues on the south elevation as well as the west elevation.
Electrician is continuing rough-in of conduit in Area B.
Painter is on second floor painting first coats in the corridor walls, soffits, as well as walls in the classrooms A210, A209, etc.
Elevator has been roughly 90% completed.
Tile has been set in the boys and girls restroom in the second floor.
Ceiling grid has been installed in classrooms A210, A209, and second floor main restrooms both boys and girls.
Westview Hills Middle School Week of July 22nd
Electrician is continuing rough-in of electrical conduit through the renovation areas A and B. Beginning to pull wire for power and lighting in the B area.
Mechanical contractor delivered and removed the existing Roof Top units for the renovation work as well as the addition work.
Plumber has completed sewage ejector pit. Continues to rough-in overhead piping throughout the renovation areas, and is working with the mason to ensure all sinks in masonry walls are properly roughed in.
Mason is roughly 90% complete with all masonry work through the addition and renovation.
Drywall is continuing to be installed in the area A FACS, band area in auditorium. Taping and finishing has begun in the art room.
First coats of painting are completed in the cafeteria, common areas of the library.
Ceiling grid is being installed in the common area of the library. Ceiling grid was completed in room C11A, C111, and C110.
Electrician has installed light fixtures in rooms C111A, C111, and C110.